Chattanooga P.W.A.                                    
Water System Improvements                                  
Bid Tabulation                                  Bid Opening Date: 11/04/02 
       Eng. Est.   John Collins   Shoestring Ent.   Miller, Inc.   Christian Construction   Rudy Box   J & S Dozer   Miller Construction 
Item Description Quan. Units  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price
Base Bid                                    
8" Cl. 160 PVC Pipe w/ftgs. 1,210 L.F. 5.50 6,655.00 3.00 3,630.00 9.00 10,890.00 4.75 5,747.50 7.50 9,075.00 10.50 12,705.00 11.00 13,310.00 7.00 8,470.00
6" Cl. 160 PVC Pipe w/ftg's 3,360 L.F. 4.50 15,120.00 2.00 6,720.00 8.94 30,038.40 4.00 13,440.00 6.45 21,672.00 3.65 12,264.00 9.40 31,584.00 6.00 20,160.00
2" Cl. 160 PVC Pipe w/ftg's 2,200 L.F. 3.00 6,600.00 1.00 2,200.00 4.55 10,010.00 1.25 2,750.00 3.00 6,600.00 2.95 6,490.00 5.00 11,000.00 3.00 6,600.00
Pipeline Standard Trenching 6,122 L.F. 4.00 24,488.00 4.00 24,488.00 1.30 7,958.60 4.75 29,079.50 4.00 24,488.00 4.00 24,488.00 6.00 36,732.00 7.00 42,854.00
8" Gate Valve w/Box 4 EA. 500.00 2,000.00 650.00 2,600.00 565.00 2,260.00 700.00 2,800.00 650.00 2,600.00 750.00 3,000.00 500.00 2,000.00 1,200.00 4,800.00
6" Gate Valve w/Box 9 EA. 450.00 4,050.00 500.00 4,500.00 418.00 3,762.00 400.00 3,600.00 550.00 4,950.00 500.00 4,500.00 450.00 4,050.00 1,000.00 9,000.00
4" Gate Valve w/Box 1 EA. 400.00 400.00 375.00 375.00 325.00 325.00 800.00 800.00 450.00 450.00 385.00 385.00 250.00 250.00 700.00 700.00
2" Gate Valve w/Box 7 EA. 300.00 2,100.00 250.00 1,750.00 252.00 1,764.00 300.00 2,100.00 275.00 1,925.00 325.00 2,275.00 220.00 1,540.00 400.00 2,800.00
Fire Hydrant 7 EA. 1,500.00 10,500.00 1,800.00 12,600.00 1,614.00 11,298.00 1,600.00 11,200.00 1,650.00 11,550.00 1,900.00 13,300.00 1,300.00 9,100.00 1,500.00 10,500.00
12" Roadway Bore 60 L.F. 50.00 3,000.00 35.00 2,100.00 48.00 2,880.00 36.00 2,160.00 35.00 2,100.00 50.00 3,000.00 75.00 4,500.00 45.00 2,700.00
12" Steel Casing 130 L.F. 30.00 3,900.00 27.00 3,510.00 18.00 2,340.00 20.00 2,600.00 12.00 1,560.00 34.60 4,498.00 10.00 1,300.00 16.00 2,080.00
10" Roadway Bore 48 L.F. 40.00 1,920.00 30.00 1,440.00 40.00 1,920.00 34.00 1,632.00 32.00 1,536.00 50.00 2,400.00 65.00 3,120.00 45.00 2,160.00
10" Steel Casing 80 L.F. 20.00 1,600.00 25.00 2,000.00 16.25 1,300.00 20.00 1,600.00 10.00 800.00 31.25 2,500.00 8.00 640.00 14.00 1,120.00
Paved Street & Drive Crossing 130 L.F. 10.00 1,300.00 30.00 3,900.00 30.00 3,900.00 38.00 4,940.00 24.00 3,120.00 40.00 5,200.00 60.00 7,800.00 36.00 4,680.00
     8" Bore & no Casing                                    
Paved Street & Drive Crossing 260 L.F. 8.00 2,080.00 25.00 6,500.00 25.00 6,500.00 28.00 7,280.00 20.00 5,200.00 40.00 10,400.00 50.00 13,000.00 36.00 9,360.00
     6" Bore & no Casing                                    
Paved Street & Drive Crossing 150 L.F. 6.00 900.00 15.00 2,250.00 15.00 2,250.00 24.00 3,600.00 10.00 1,500.00 25.00 3,750.00 40.00 6,000.00 27.00 4,050.00
     2" Bore & no Casing                                    
Abandon Waterline 2 EA. 500.00 1,000.00 300.00 600.00 240.00 480.00 850.00 1,700.00 450.00 900.00 750.00 1,500.00 100.00 200.00 500.00 1,000.00
3/4" Service Line Piping 510 L.F. 3.00 1,530.00 10.00 5,100.00 12.00 6,120.00 6.50 3,315.00 3.75 1,912.50 5.88 2,998.80 3.00 1,530.00 6.00 3,060.00
Water Service Connection 51 EA. 300.00 15,300.00 350.00 17,850.00 154.07 7,857.57 250.00 12,750.00 325.00 16,575.00 250.00 12,750.00 100.00 5,100.00 350.00 17,850.00
Constr. Surveying on SH 36 1 L.Sum 2,000.00 2,000.00 5,000.00 5,000.00 1,900.00 1,900.00 3,000.00 3,000.00 600.00 600.00 1,800.00 1,800.00 1,000.00 1,000.00 5,000.00 5,000.00
Total Base Bid       106,443.00   109,113.00   115,753.57   116,094.00   119,113.50   130,203.80   153,756.00   158,944.00
                                     
Add. Alternate #1                                    
Unpaved Driveway Crossing 325 L.F. 5.00 1,625.00 20.00 6,500.00 27.00 8,775.00 15.00 4,875.00 24.00 7,800.00 9.23 2,999.75 8.00 2,600.00 25.00 8,125.00
Trench & Backfill                                    
 Total Add. Alternate #1       1,625.00   6,500.00   8,775.00   4,875.00   7,800.00   2,999.75   2,600.00   8,125.00
                                     
Add. Alternate #1                                    
Unpaved Driveway Crossing 75 L.F. 10.00 750.00 30.00 2,250.00 30.00 2,250.00   2,250.00 24.00 1,800.00 40.00 3,000.00 60.00 4,500.00 36.00 2,700.00
     8" Bore & no Casing                                    
Unpaved Driveway Crossing 210 L.F. 8.00 1,680.00 25.00 5,250.00 25.00 5,250.00   5,040.00 20.00 4,200.00 40.00 8,400.00 50.00 10,500.00 36.00 7,560.00
     6" Bore & no Casing                                    
Unpaved Driveway Crossing 40 L.F. 6.00 240.00 15.00 600.00 15.00 600.00   800.00 10.00 400.00 25.00 1,000.00 1,600.00 27.00 1,080.00
     2" Bore & no Casing                                    
Total Add. Alternate #2        $       2,670.00    $      8,100.00    $       8,100.00    $      8,090.00    $      6,400.00    $    12,400.00    $    16,600.00    $    11,340.00
   *  Bid extension math error corrected.