Town of Sterling                                    
Waterline Improvements                    
Bid Tabulation              Bid Opening Date: 12/12/02       
       Eng. Est.   JTM Services   Collins Construction   Christian Construction   Miller, Inc.   Shoestring Ent.   Bowen Construction   Miller Constr. & Sons 
Item Description Quan. Units  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price  Unit Price  Total Price
Base Bid                                    
6" Cl. 160 PVC Pipe w/ftg's 6,020 L.F. 4.50 27,090.00 1.96 11,799.20 2.50 15,050.00 3.86 23,237.20 2.60 15,652.00 5.63 33,892.60 7.00 42,140.00 6.10 36,722.00
Pipeline Standard Trenching 5,375 L.F. 4.00 21,500.00 3.27 17,576.25 3.50 18,812.50 3.00 16,125.00 4.00 21,500.00 1.20 6,450.00 1.00 5,375.00 3.10 16,662.50
6" Gate Valve w/Box 7 EA. 450.00 3,150.00 468.21 3,277.47 400.00 2,800.00 475.00 3,325.00 375.00 2,625.00 555.00 3,885.00 500.00 3,500.00 1,000.00 7,000.00
4" Gate Valve w/Box 2 EA. 400.00 800.00 327.21 654.42 300.00 600.00 315.00 630.00 360.00 720.00 525.00 1,050.00 500.00 1,000.00 800.00 1,600.00
2" Gate Valve w/Box 2 EA. 300.00 600.00 272.50 545.00 275.00 550.00 250.00 500.00 250.00 500.00 375.00 750.00 500.00 1,000.00 400.00 800.00
Fire Hydrant 6 EA. 1,500.00 9,000.00 1,873.15 11,238.90 1,675.00 10,050.00 1,500.00 9,000.00 1,550.00 9,300.00 1,600.00 9,600.00 1,847.00 11,082.00 1,500.00 9,000.00
Remove Fire Hydrant 4 EA. 500.00 2,000.00 218.00 872.00 90.00 360.00 200.00 800.00 400.00 1,600.00 350.00 1,400.00 125.00 500.00 500.00 2,000.00
Paved Street & Drive Crossing 360 L.F. 30.00 10,800.00 16.35 5,886.00 25.00 9,000.00 20.00 7,200.00 24.00 8,640.00 25.00 9,000.00 30.00 10,800.00 45.00 16,200.00
     6" Bore & no Casing                                    
Abandon Waterline 1 EA. 500.00 500.00 109.00 109.00 350.00 350.00 300.00 300.00 250.00 250.00 225.00 225.00 2,500.00 2,500.00 1,500.00 1,500.00
3/4" Service Line Piping 410 L.F. 3.00 1,230.00 1.09 446.90 5.00 2,050.00 2.85 1,168.50 3.00 1,230.00 4.20 1,722.00 10.00 4,100.00 2.50 1,025.00
Water Service Connection 41 EA. 300.00 12,300.00 163.50 6,703.50 175.00 7,175.00 150.00 6,150.00 200.00 8,200.00 220.00 9,020.00 125.00 5,125.00 400.00 16,400.00
Total Base Bid       88,970.00   59,108.64   66,797.50   68,435.70   70,217.00   76,994.60   87,122.00   108,909.50
                                     
Add. Alternate #1                                    
Unpaved Driveway Crossing 285 L.F. 20.00 5,700.00 10.00 2,850.00 20.00 5,700.00 17.50 4,987.50 6.00 1,710.00 20.00 5,700.00 2.00 570.00 25.00 7,125.00
Trench & Backfill                                    
 Total Add. Alternate #1       5,700.00   2,850.00   5,700.00   4,987.50   1,710.00   5,700.00   570.00   7,125.00
                                     
Add. Alternate #2                                    
Unpaved Driveway Crossing 285 L.F. 30.00 8,550.00 16.35 4,659.75 30.00 8,550.00 20.00 5,700.00 24.00 6,840.00 25.00 7,125.00 30.00 8,550.00 45.00 12,825.00
     6" Bore & no Casing                                    
Total Add. Alternate #2        $      8,550.00    $      4,659.75    $     8,550.00    $     5,700.00    $     6,840.00    $     7,125.00    $      8,550.00    $      12,825.00
 *  Bid extension math error corrected.