| Town of Hastings | |||||||||||||||||||||
| Waterline Improvements | |||||||||||||||||||||
| Bid Tabulation | Bid Opening Date: 4/4/02 | ||||||||||||||||||||
| Engineer's Estimate | Collins Construction | England Plumbing | Miller, Inc. | M.L. Young | Garcia Construction | Miller Construction | Bowles Construction | Rudy Box | |||||||||||||
| Item Description | Quan. | Units | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | |
| 6" Cl. 200 PVC Pipe | 2,620 | L.F. | 4.50 | 11,790.00 | 2.50 | 6,550.00 | 3.00 | 7,860.00 | 3.25 | 8,515.00 | 4.00 | 10,480.00 | 4.00 | 10,480.00 | 4.00 | 10,480.00 | 13.00 | 34,060.00 | 3.81 | 9,982.20 | |
| 6" Gate Valve w/Box | 10 | EA. | 450.00 | 4,500.00 | 385.00 | 3,850.00 | 500.00 | 5,000.00 | 365.00 | 3,650.00 | 450.00 | 4,500.00 | 500.00 | 5,000.00 | 1,200.00 | 12,000.00 | 475.00 | 4,750.00 | 500.00 | 5,000.00 | |
| Pipeline Standard Trenching | 2,500 | L.F. | 4.00 | 10,000.00 | 3.25 | 8,125.00 | 3.00 | 7,500.00 | 3.50 | 8,750.00 | 7.00 | 17,500.00 | 8.00 | 20,000.00 | 3.10 | 7,750.00 | 2.00 | 5,000.00 | 10.00 | 25,000.00 | |
| 4" Gate Valve w/Box | 4 | EA. | 375.00 | 1,500.00 | 300.00 | 1,200.00 | 400.00 | 1,600.00 | 285.00 | 1,140.00 | 370.00 | 1,480.00 | 350.00 | 1,400.00 | 1,000.00 | 4,000.00 | 375.00 | 1,500.00 | 450.00 | 1,800.00 | |
| 2" Gate Valve w/Box | 2 | EA. | 300.00 | 600.00 | 250.00 | 500.00 | 300.00 | 600.00 | 200.00 | 400.00 | 260.00 | 520.00 | 250.00 | 500.00 | 875.00 | 1,750.00 | 275.00 | 550.00 | 400.00 | 800.00 | |
| Fire Hydrant | 3 | EA. | 1,500.00 | 4,500.00 | 1,550.00 | 4,650.00 | 1,500.00 | 4,500.00 | 1,550.00 | 4,650.00 | 1,650.00 | 4,950.00 | 1,500.00 | 4,500.00 | 1,500.00 | 4,500.00 | 1,200.00 | 3,600.00 | 1,500.00 | 4,500.00 | |
| Dr. & Str. Cross. - 6" Bore | 5 | EA. | 430.00 | 2,150.00 | 1,000.00 | 5,000.00 | 900.00 | 4,500.00 | 800.00 | 4,000.00 | 1,000.00 | 5,000.00 | 600.00 | 3,000.00 | 800.00 | 4,000.00 | 1,000.00 | 5,000.00 | 1,600.00 | 8,000.00 | |
| Abandon Waterline | 2 | EA. | 400.00 | 800.00 | 500.00 | 1,000.00 | 400.00 | 800.00 | 600.00 | 1,200.00 | 1,000.00 | 2,000.00 | 500.00 | 1,000.00 | 1,000.00 | 2,000.00 | 500.00 | 1,000.00 | 800.00 | 1,600.00 | |
| 3/4" Service Line Piping | 110 | L.F. | 3.00 | 330.00 | 5.00 | 550.00 | 2.00 | 220.00 | 6.00 | 660.00 | 5.00 | 550.00 | 7.00 | 770.00 | 5.00 | 550.00 | 9.00 | 990.00 | 5.00 | 550.00 | |
| Water Service Connection | 11 | EA. | 300.00 | 3,300.00 | 120.00 | 1,320.00 | 150.00 | 1,650.00 | 450.00 | 4,950.00 | 125.00 | 1,375.00 | 300.00 | 3,300.00 | 400.00 | 4,400.00 | 300.00 | 3,300.00 | 300.00 | 3,300.00 | |
| Total Base Bid | 39,470.00 | 32,745.00 | 34,230.00 | 37,915.00 | 48,355.00 | 49,950.00 | 51,430.00 | 59,750.00 | 60,532.20 | ||||||||||||
| Add. Alternate #1 | |||||||||||||||||||||
| Gravel Dr. Cross. - 6" Bore | 9 | EA. | 400.00 | 3,600.00 | 750.00 | 6,750.00 | 900.00 | 8,100.00 | 800.00 | 7,200.00 | 400.00 | 3,600.00 | 500.00 | 4,500.00 | 800.00 | 7,200.00 | 900.00 | 8,100.00 | 800.00 | 7,200.00 | |
| Total Bid - Alternate #1 | $ 3,600.00 | $ 6,750.00 | $ 8,100.00 | $ 7,200.00 | $ 3,600.00 | $ 4,500.00 | $ 7,200.00 | $ 8,100.00 | $ 7,200.00 | ||||||||||||
| * Bid extension math error corrected. | |||||||||||||||||||||