| Town of Alex | ||||||||
| Test Well | ||||||||
| Bid Tabulation | ||||||||
| Eng. Est. | Layne Christensen | Bowen Construction | ||||||
| Item Description | Quan. | Units | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price |
| Mobilization | 1 | L.Sum | 2,000.00 | 2,000.00 | 2,750.00 | 2,750.00 | 2,130.00 | 2,130.00 |
| Drill 8" Test Well | 100 | V.F. | 50.00 | 5,000.00 | 30.00 | 3,000.00 | 75.42 | 7,542.00 |
| Well Logging | 1 | L.Sum | 2,500.00 | 2,500.00 | 2,250.00 | 2,250.00 | 3,695.00 | 3,695.00 |
| Isolate & Sample Zones | 5 | EA. | 200.00 | 1,000.00 | 1,500.00 | 7,500.00 | 2,260.00 | 11,300.00 |
| Seal Test Well | 1 | L.Sum | 500.00 | 500.00 | 1,000.00 | 1,000.00 | 1,723.00 | 1,723.00 |
| Geologist/Hydrologist Report | 1 | L.Sum | 500.00 | 500.00 | 1,000.00 | 1,000.00 | 2,356.00 | 2,356.00 |
| Total Bid Price | 11,500.00 | 17,500.00 | 28,746.00 | |||||
| * Bid extension math error corrected. | ||||||||
| H. Lester Seiger, P.E., P.L.S. | ||||||||