| City of Snyder | ||||||
| US 183 Waterline & Sewerline Relocation | ||||||
| Bid Tabulation | ||||||
| Eng. Est. | Shoestring Enterprises | |||||
| Item Description | Quan. | Units | Unit Price | Total Price | Unit Price | Total Price |
| Waterline Construction | ||||||
| 10" Cl. 160 PVC Pipe w/ftg's | 330 | L.F. | 6.50 | 2,145.00 | 50.00 | 16,500.00 |
| 6" Cl. 160 PVC Pipe w/ftg's | 4,340 | L.F. | 4.50 | 19,530.00 | 12.00 | 52,080.00 |
| 4" Cl. 160 PVC Pipe w/ftg's | 2,200 | L.F. | 3.50 | 7,700.00 | 10.00 | 22,000.00 |
| 2" Cl. 160 PVC Pipe w/ftg's | 3,380 | L.F. | 2.50 | 8,450.00 | 8.00 | 27,040.00 |
| Trenching 4' Depth | 9,730 | L.F. | 4.00 | 38,920.00 | 11.00 | 107,030.00 |
| Trenching 30" Depth | 2,230 | L.F. | 3.00 | 6,690.00 | 9.00 | 20,070.00 |
| 10" Gate Valve w/Box | 3 | EA. | 650.00 | 1,950.00 | 1,700.00 | 5,100.00 |
| 6" Gate Valve w/Box | 24 | EA. | 430.00 | 10,320.00 | 750.00 | 18,000.00 |
| 4" Gate Valve w/Box | 8 | EA. | 390.00 | 3,120.00 | 500.00 | 4,000.00 |
| 2" Gate Valve w/Box | 3 | EA. | 300.00 | 900.00 | 300.00 | 900.00 |
| 14" Road Bore | 110 | L.F. | 50.00 | 5,500.00 | 85.00 | 9,350.00 |
| 10" Road Bore | 76 | L.F. | 45.00 | 3,420.00 | 50.00 | 3,800.00 |
| 8" Road Bore | 162 | L.F. | 40.00 | 6,480.00 | 40.00 | 6,480.00 |
| 14" Steel Casing | 200 | L.F. | 30.00 | 6,000.00 | 25.00 | 5,000.00 |
| 10" Steel Casing | 76 | L.F. | 25.00 | 1,900.00 | 15.00 | 1,140.00 |
| 8" Steel Casing | 244 | L.F. | 20.00 | 4,880.00 | 10.00 | 2,440.00 |
| Relocate Water Meter | 50 | EA. | 200.00 | 10,000.00 | 350.00 | 17,500.00 |
| Remove Fire Hydrant & Valve | 7 | EA. | 300.00 | 2,100.00 | 1,000.00 | 7,000.00 |
| 2" Steel Vent Pipe | 50 | L.F. | 4.00 | 200.00 | 10.00 | 500.00 |
| Street/Driveway Crossing (1) | 51 | EA. | 500.00 | 25,500.00 | 870.00 | 44,370.00 |
| Street/Driveway Crossing (2) | 15 | EA. | 200.00 | 3,000.00 | 870.00 | 13,050.00 |
| Street/Driveway Crossing (3) | 3 | EA. | 400.00 | 1,200.00 | 870.00 | 2,610.00 |
| Street/Driveway Crossing (4) | 2 | EA. | 100.00 | 200.00 | 870.00 | 1,740.00 |
| Fire Hydrant | 7 | EA. | 1,500.00 | 10,500.00 | 2,000.00 | 14,000.00 |
| Sub-Total Waterline Constr. | 180,605.00 | 401,700.00 | ||||
| Sewer line Construction | ||||||
| 8" DR35 PVC Sewer Pipe | 1,178 | L.F. | 5.00 | 5,890.00 | 10.00 | 11,780.00 |
| 4' Dia. Manhole | 7 | 1400 | 1,400.00 | 9,800.00 | 1,200.00 | 8,400.00 |
| 4' Dia. Manhole, Ex. Depth | 41.7 | V.F. | 130.00 | 5,421.00 | 250.00 | 10,425.00 |
| Trench & Backfill (0-6') | 527 | L.F. | 9.00 | 4,743.00 | 30.00 | 15,810.00 |
| Trench & Backfill (6-8') | 317 | L.F. | 12.00 | 3,804.00 | 35.00 | 11,095.00 |
| Trench & Backfill (12-14') | 75 | L.F. | 22.00 | 1,650.00 | 40.00 | 3,000.00 |
| Trench & Backfill (14-16') | 75 | L.F. | 25.00 | 1,875.00 | 45.00 | 3,375.00 |
| Sewer Service Connection | 10 | EA. | 350.00 | 3,500.00 | 500.00 | 5,000.00 |
| Sewer Service Line (4" or 6") | 100 | L.F. | 9.00 | 900.00 | 15.00 | 1,500.00 |
| Street/Driveway Cross. (3) | 3 | EA. | 400.00 | 1,200.00 | 1,000.00 | 3,000.00 |
| 12" Bore | 120 | L.F. | 75.00 | 9,000.00 | 100.00 | 12,000.00 |
| 12" Steel Casing | 100 | L.F. | 18.00 | 1,800.00 | 20.00 | 2,000.00 |
| Abandon Manhole | 2 | EA. | 650.00 | 1,300.00 | 1,000.00 | 2,000.00 |
| Subtotal Sewer Line Constr. | 50,883.00 | 89,385.00 | ||||
| Total Bid Price | $ 231,488.00 | $ 491,085.00 | ||||
| H. Lester Seiger, P.E. | * Bid extension math error corrected. | |||||
| Landmark Engineering | ||||||