| Town of
Faxon |
|
|
|
|
|
|
|
| Water Tank Project |
|
|
|
|
| Bid Tabulation |
|
Bid Opening Date |
11/3/2005 |
|
| |
|
|
Engineer's |
Circle-P |
Bowen |
Tank |
|
| |
|
|
Estimate |
Welding |
Contractors |
Builders |
|
| Item Description |
Quan. |
Units |
Total Price |
Total Price |
Total Price |
Total Price |
|
| Contract #1 - Standpipe Construction |
|
|
|
|
|
|
|
| Foundation |
1 |
L.S. |
37,200.00 |
27,700.00 |
29,070.00 |
17,847.00 |
|
| Tank Fabrication & Erection |
1 |
L.S. |
99,400.00 |
79,103.00 |
120,344.00 |
88,706.00 |
|
| Interior Painting |
1 |
L.S. |
14,000.00 |
10,000.00 |
9,895.00 |
12,500.00 |
|
| Exterior Painting |
1 |
L.S. |
16,200.00 |
8,000.00 |
9,895.00 |
12,500.00 |
|
| Piping, Valves, Vaults, etc. |
1 |
L.S. |
12,200.00 |
12,900.00 |
18,000.00 |
16,752.00 |
|
| Paint Lettering |
1 |
L.S. |
600.00 |
800.00 |
1,000.00 |
1,500.00 |
|
| Fence |
1 |
L.S. |
1,600.00 |
3,800.00 |
6,200.00 |
4,800.00 |
|
| Crushed Limestone Paving |
1 |
L.S. |
1,300.00 |
800.00 |
1,500.00 |
4,460.00 |
|
| Cleanup |
1 |
L.S. |
300.00 |
500.00 |
1,200.00 |
1,264.00 |
|
| 8th Street Paving Repair |
1 |
L.S. |
3,000.00 |
1,500.00 |
1,200.00 |
1,064.00 |
|
| Contract #1 - Total Bid Price |
|
|
185,800.00 |
145,103.00 |
198,304.00 |
161,393.00 |
|
| |
|
|
|
|
|
|
|
| Contract #2 - Tank Removal |
|
|
|
|
|
|
|
| Remove Elevated Tank |
1 |
L.S. |
5,000.00 |
|
25,000.00 |
|
|
| Connect Existing Waterlines |
1 |
L.S. |
1,000.00 |
|
2,000.00 |
|
|
| Cleanup |
1 |
L.S. |
300.00 |
|
1,500.00 |
|
|
| Contract #2 -
Total Bid Price |
|
|
6,300.00 |
No Bid |
28,500.00 |
No Bid |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| H. Lester Seiger, P.E., P.L.S. |
|
|
|
|
| Landmark Engineering |
|
|
|
|
|
|
|
|
|
|
|
|