| Town of Hydro | ||||||||||
| Water Well | ||||||||||
| Bid Tabulation | Bid Opening Date: 6/1/2005 | |||||||||
| Eng. Est. | Resource Builders | Bowen Construction | Shoestring Ent. | |||||||
| Item Description | Quan. | Units | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price |
| SDR26 PVC Surface Casing | 20 | V.F. | 75.00 | 1,500.00 | 224.00 | 4,480.00 | 61.00 | 1,220.00 | 80.50 | 1,610.00 |
| 12" Borehole | 270 | V.F. | 36.00 | 9,720.00 | 56.00 | 15,120.00 | 93.00 | 25,110.00 | 69.00 | 18,630.00 |
| Well Logging | 1 | L.Sum | 2,680.00 | 2,680.00 | 1,120.00 | 1,120.00 | 4,240.00 | 4,240.00 | 2,300.00 | 2,300.00 |
| Well Casing | 270 | V.F. | 18.00 | 4,860.00 | 6.00 | 1,620.00 | 4.57 | 1,233.90 | 4.69 | 1,266.30 |
| Grout Seal | 20 | V.F. | 120.00 | 2,400.00 | 15.00 | 300.00 | 36.96 | 739.20 | 37.95 | 759.00 |
| Gravel Pack | 270 | V.F. | 16.00 | 4,320.00 | 3.00 | 810.00 | 8.35 | 2,254.50 | 8.52 | 2,300.40 |
| Well Screen | 20 | V.F. | 100.00 | 2,000.00 | 8.00 | 160.00 | 5.88 | 117.60 | 6.04 | 120.80 |
| Alignment Test | 1 | L.Sum | 1,000.00 | 1,000.00 | 500.00 | 500.00 | 100.00 | 100.00 | 1,500.00 | 1,500.00 |
| Well Development | 1 | L.Sum | 3,000.00 | 3,000.00 | 9,500.00 | 9,500.00 | 6,104.00 | 6,104.00 | 6,267.50 | 6,267.50 |
| Building Foundation | 1 | L.Sum | 3,000.00 | 3,000.00 | 3,000.00 | 3,000.00 | 2,000.00 | 2,000.00 | 6,500.00 | 6,500.00 |
| CMU Building & Roof | 1 | L.Sum | 8,000.00 | 8,000.00 | 14,500.00 | 14,500.00 | 10,775.00 | 10,775.00 | 17,250.00 | 17,250.00 |
| Well House Electrical | 1 | L.Sum | 7,000.00 | 7,000.00 | 7,300.00 | 7,300.00 | 7,922.00 | 7,922.00 | 8,500.00 | 8,500.00 |
| Well House Piping | 1 | L.Sum | 4,000.00 | 4,000.00 | 4,750.00 | 4,750.00 | 4,000.00 | 4,000.00 | 12,000.00 | 12,000.00 |
| Pump & Controls | 1 | L.Sum | 5,000.00 | 5,000.00 | 9,200.00 | 9,200.00 | 7,558.00 | 7,558.00 | 14,542.90 | 14,542.90 |
| Chlorine Pump amd Drum | 1 | L.Sum | 1,000.00 | 1,000.00 | 2,500.00 | 2,500.00 | 2,500.00 | 2,500.00 | 3,250.00 | 3,250.00 |
| Total Bid Price | 59,480.00 | 74,860.00 | 75,874.20 | 96,796.90 | ||||||
| * Bid extension math error corrected. | ||||||||||
| Landmark Engineering | ||||||||||